Ahlerstedt battery storage (Oersdorf)

15 MW
30 MWh
1,300 m²
06/01/2026
The project was implemented in several consecutive phases with clear milestones.
02/2025
Site planning and contract conclusion
Completion of site planning and final contractual agreement with the property owner as a basis for project implementation.

04/2025
Site ready for construction
The site is fully prepared and all contractual and organizational requirements for the start of construction have been met.

06/2025
Groundbreaking and start of construction
Official start of construction and implementation of the on-site battery storage system.

09/2025
Delivery and installation of battery containers
Delivery and installation of eight battery containers, including technical integration at the site.

11/2025
Energizing the plant
Completion of foundation work and initial energization of the battery storage system.

12/2025
Performance testing and commissioning
Conducting performance and functional tests and performing the initial charge and discharge of the battery storage system.

01/2026
Start of commercial operations
Start of regular commercial operation of the battery storage system within the energy grid.

The project has a demonstrable effect on grid operation and energy flow.
15 MW
In this way, you can react flexibly to price signals and continuously increase revenue potential.
30 MWh
optimization
Owners & Project Developers
project development
Construction/Operation/ Maintenance
Network connection & coordination
funding

“Terra One is positioning itself as a leading innovator in the field of battery storage and is making a decisive contribution to stabilizing the energy revolution. ”
Let us evaluate your battery storage project.