Barsinghausen battery storage facility

15 MW
60 MWh
3,700 m²
Q4 2026
The project was implemented in several consecutive phases with clear milestones.
Q4/2023
Site Securing & Grid Capacity Inquiry
At the end of 2023, we secured a site in Barsinghausen, Lower Saxony, approximately half an hour west of Hanover. In parallel with the land use contract negotiations, the necessary grid connection processes were initiated, including a 15MW inquiry with the responsible grid operator, Avacon.

Q1/2024
Building permit application submitted
Following the acquisition of the necessary expert reports (including fire, noise, and water protection) and site planning that accounts for adjacent gas pipelines, the building permit application will be submitted to the municipality of Barsinghausen in the Hanover region in March 2024.

Q4/2024
Announcement of CCI project acquisition
In November 2024, the acquisition of project rights totaling 310 MW by CCI was announced. Capcora supported Terra One in executing this M&A deal. The Barsinghausen project, a battery storage development, is included in the acquisition.

Henning Prigge, Director at Capcora
"This transaction marks a milestone for the German battery storage market. Terra One has demonstrated that large-scale BESS portfolios can already mobilize significant institutional capital today, provided that projects are technically sound, structurally well-organized, and strategically positioned. We are proud to have supported Terra One in setting a new benchmark for the market."

Q4/2024
Building permit approval
Shortly thereafter, in December 2024, Terra One received the building permit for the Barsinghausen project from the responsible building authority. In addition, we received confirmation for the grid connection at the corresponding substation. This marks the start of the next project phase.

Q4/2025
Project is "ready-to-build"
Upon receipt of the pending grid connection agreement, the necessary grid connection commitment, and the fulfillment of additional requirements such as solid financing, the Barsinghausen battery storage project will be "ready-to-build."

Maximilian Bodewein, Vice President of Development at Terra One
"With the development and sale of the Barsinghausen project, our team has proven that it can achieve ambitious goals in a short timeframe. From submitting the necessary documentation to coordinating multiple stakeholders, our team has demonstrated its ability to execute project development and coordination at the highest level and with maximum speed."

Crucial for Lower Saxony's energy goals
15 MW
In this way, you can react flexibly to price signals and continuously increase revenue potential.
60 MWh
optimization
Owners & Project Developers
project development
Construction/Operation/ Maintenance
Network connection & coordination
funding

“Terra One is positioning itself as a leading innovator in the field of battery storage and is making a decisive contribution to stabilizing the energy revolution. ”
Let us evaluate your battery storage project.